January Time Lapse Video

2nd février 2016

Work on the new Dyehouse in January 2016 saw the safety railing & safety netting being put in place in preparation for the roof installation which is underway.
The brick and block work is progressing and will be built up to floor level in preparation for the flooring. The shuttering has also been completed on the lids of the effluent and cooling chambers.

The recent high winds and rain are creating many challenges on site. The weather maps are being closely watched to progress the roofing which is planned to be complete in early March. The installation of two large silo tanks, which will be set in place on the mezzanine floor, are also planned although a calm day is required.

We have continued to capture the progress with time-lapse photography and have prepared a video of the work in January 2016 and a project to date video which you can view below.

There are also still images showing on our Contract (Sustainability/New Developments) & Residential (About / Profile/Dye House) websites.

Please enjoy the 5th video in the series together with the 2nd Project to Date video.