June 2016 Timelapse Videos

6th July 2016

Continuing throughout June the weather maps have been under intense scrutiny in planning the delivery of concrete for the newly levelled ground outside the Dyehouse and has seen the rear yard and main ramps concreted despite the rain.

Inside the new Dyehouse work has continued. The shuttle rails are located and we now have 80% of the new dyeing machinery set into place, the mezzanine floor office area and the lift shaft both nearing completion.

All of the lights and sockets are working in the Dyehouse and during July, work will continue in the electrical wiring up of the machines and the plumbing of the piping to connect the machines. Also in July the next phase in the changeover to high voltage electricity will take place and the concreting of the apron (ground) outside will be finished.

You can keep up to date with our time lapse photography on both our Contract and Residential websites and via our social media pages.