Month 2 – Time Lapse Video

28th octobre 2015

Work has continued throughout October on the foundations of the new Dyehouse with approximately 2,700 metres of concrete piling completed in September.  Work on the ground beams and ‘holding down’ bolts for the main steel structure has progressed throughout October and this part of the project is expected to keep going until end November 2015.  The main drainage system is now 90% complete and they are working towards the last manhole.