Month 1 – Time Lapse video

1st October 2015

Month 1 has seen excellent progress been made on the foundations of the new building of Ulsters Dyehouse and Energy Centre . Piling work is now completed ahead of schedule with 255 piles in the ground.

Work has now begun on digging the channels and the bespoke re-bar framework fabrication for the ground beams. This stage will take approximately 2 months.

We have been able to capture the progress with time-lapse photography and video. Please see Month 1’s progress video below and don’t forget you can keep up-to-date with the photography aspect Here.